Construction and Traffic Updates

Posted on: March 28, 2019

Construction to Resume on Coral Ridge Avenue

CoralRidgeAve_OakdaleForevergreen_300

Construction on Coral Ridge Avenue between Oakdale Boulevard and Forevergreen Road will start again on Tuesday, April 2. 

The initial focus will be on completing final street, median, and sidewalk construction on the east half of Coral Ridge Avenue between University Parkway and Forevergreen Road. This will require running traffic head-to-head on the west half of Coral Ridge Avenue between University Parkway and Forevergreen Road, similar to the traffic control setup last fall. Coral Ridge Avenue will remain in this configuration until mid-to-late May, and then traffic will shift to single lanes northbound and southbound, but on the correct side of the center median, until the project is completed.

Reminders for drivers:

  • Take it slow through the project corridor.
  • Help other drivers merge into your lane.
  • Please keep an eye out for pedestrians, bicyclists, and construction workers.
  • If possible, adjust your schedule to avoid the morning and afternoon rush hours.

The Coral Ridge Avenue project should be complete by the end of June.